Beginning Monday, November 16, 2026, Gardner Excavating will begin sewer replacements on portions of Silver Drive. This project is expected to last until Friday, November 20, 2026, however, the scope of work is highly dependent on weather conditions.
Attached is the map of the work area, highlighted in orange. Their work schedule is outlined below:
- November 16th - November 18th: Gardner Excavating plans to work in the highlighted orange area in front of 9 Silver Drive, 17 Silver Drive, and 25 Silver Drive. This section of the road in front of those addresses will be closed to through traffic from 7am to 5pm.
- November 19th - November 20th: Gardner Excavating plans to work in the highlighted orange area in front of 51 Silver Drive and 49 Silver Drive. This part of the road in front of those addresses will be closed to through traffic from 7am to 5pm.
Gardner Excavating will not work in both orange highlighted areas simultaneously, allowing residents to detour the loop as needed. Although this is the planned work schedule, again, this work remains highly weather-dependent. We ask residents to plan accordingly and drive carefully in this area for the workers’ safety.
Please help spread the word about these road closures. For any questions or concerns, please email or call Public Works Director, Scott Johnson, at 719-658-2276 x. 4. His email is publicworks@creedetownhall.com and is also attached to this email. We thank residents for their anticipated patience and cooperation during this sewer upgrade project.